The Megawatt Charging System (MCS) is a charging standard designed for heavy electric vehicles such as trucks. It lets a vehicle take far more power than today’s car and van chargers, so large batteries can be topped up in a driver’s break.
This guide explains what MCS is, how it compares with CCS, and what it means if you are planning an HGV depot in the UK.
Not to be confused with MCS certification, the scheme for solar and heat pump installers. The two are unrelated.
What is the Megawatt Charging System?
MCS was started by CharIN, the industry association behind the Combined Charging System (CCS), which set up an MCS task force in 2018. It builds on CCS but uses a new, single connector for commercial vehicles (CharIN).
CharIN lists a maximum of 1,250 volts and 3,000 amps DC. Multiply the two and you get 3.75MW. In 2026 CharIN reported the official publication of IEC TS 63379, a technical specification for MCS (CharIN, checked 16 November 2026).
Real chargers and trucks will deliver less than the maximum, depending on the charger, the vehicle’s battery and how full it is.
MCS vs CCS
- CCS is the DC standard used by cars, vans and most electric trucks today. It covers a wide range of power, from depot chargers to high-power units.
- MCS uses a different, larger connector designed for higher currents, for vehicles with very large batteries.
- A truck can only use MCS if it has an MCS inlet. Many trucks on the road today charge on CCS.
For a wider look at depot options, see our electric HGV charging page.
Why megawatt charging matters
Long-haul trucks cannot wait hours to charge. Under the drivers’ hours rules, drivers must take breaks totalling at least 45 minutes after no more than 4 hours 30 minutes of driving (GOV.UK). Very high-power charging aims to add meaningful range in that kind of window.
Government expects depot charging to be the foundation of the HGV network, supplemented by shared and en-route charging as demand grows (GOV.UK Find a Grant, checked 16 November 2026). Megawatt charging is most relevant to that en-route and shared layer.
Is megawatt charging in the UK yet?
Yes, at early sites. The ZEHID demonstrator programme’s 2026 report describes the eFreight 2030 project as delivering the UK’s first megawatt-scale charging hubs. Across ZEHID, installations range from a 43kW charger to a 5MW facility of ultra-rapid chargers (ZEHID annual report 2026).
Does your depot need MCS?
Usually not yet. Most depot charging happens overnight or during long dwell times, when lower-power CCS charging is cheaper and puts less strain on the supply.
MCS becomes worth considering if your trucks run double shifts, have short turnarounds, or the depot will serve other operators.
Either way, it pays to plan ahead:
- Leave space, ducting and switchgear capacity for higher-power chargers later.
- Size bays for tractor units and trailers.
- Plan the grid connection in phases with your network operator.
- Consider battery storage to buffer high-power sessions.
The power question
One megawatt-scale charger can need more power than many existing depots use in total. Cenex gives indicative costs of £60,000 to £2 million, and six months or more, for connections above 1,000kVA (Cenex, accessed November 2026). Read our guide to HGV depot grid connections.
Battery storage, load management and on-site solar can reduce the peak the grid has to supply.
Grants
The Depot Charging Scheme pays 60% of eligible chargepoint and civil costs at fleet depots, up to £1 million, with applications closing at midday on 26 February 2027 (GOV.UK Find a Grant, checked 16 November 2026). Public on-route charging sites are not in scope. See HGV and electric truck charging grants.
Frequently asked questions
What is the Megawatt Charging System?
The Megawatt Charging System (MCS) is a DC charging standard for heavy electric vehicles, developed through CharIN. CharIN lists a maximum of 1,250 volts and 3,000 amps, or 3.75MW.
Is MCS the same as CCS?
No. MCS builds on CCS but uses a different, larger connector for much higher currents. A truck needs an MCS inlet to use an MCS charger.
Do I need megawatt charging at my depot?
Most depots do not need it yet, because trucks parked overnight can charge at lower power. It is worth planning space and capacity for higher-power charging later.
Is the Megawatt Charging System related to MCS certification?
No. MCS certification is a quality scheme for solar and heat pump installers. The Megawatt Charging System is a vehicle charging standard.
Are there megawatt chargers in the UK?
Yes, at early sites. The ZEHID 2026 annual report describes the UK’s first megawatt-scale charging hubs being delivered through the eFreight 2030 project.
Plan your truck charging
Tell us about your site, your vehicles and when they park. We will look at your supply, your roof and your options, then send a clear, no-obligation proposal.
See electric HGV charging and model costs with the solar and EV charging calculator.