If you are moving trucks to electric, there is funding for both the vehicles and the depot chargers. This guide covers every UK scheme we could confirm from official sources, with dates, as at 16 November 2026.
Deadline: Depot Charging Scheme applications close at midday on 26 February 2027, or sooner if the £38 million budget is used up. Applications are assessed first come, first served unless the window is oversubscribed.
Quick summary
- Depot Charging Scheme (window 2): open now. 60% of chargepoint and civil costs, up to £1 million. Closes 26 February 2027.
- Zero Emission Truck Grant: open. Up to 40% off a new zero-emission truck, capped at £15,000 to £81,000 by weight. Runs to 31 March 2030 or until funds run out.
- 100% first-year allowance on chargepoints: equipment bought before April 2027.
- Full expensing: may apply to new trucks bought by companies.
- Scottish Zero Emission Truck Fund: proposed, for consortia in Scotland. Launch date not yet announced.
- ZEHID: a closed demonstration programme, not open for applications.
Depot Charging Scheme (window 2)
The Depot Charging Scheme part-funds charging infrastructure at fleet depots for battery-electric vans, HGVs and coaches. It is part of a £170 million programme running from April 2026 to 2030 (GOV.UK Find a Grant, checked 16 November 2026).
- Applications open: 11 November 2026 (midday).
- Applications close: 26 February 2027 (midday), or earlier if the £38 million budget runs out.
- Grant rate: 60% of chargepoint and civil costs.
- Cap: £1 million per organisation across all sites. Projects costing more than £1.67 million receive the £1 million maximum.
- Award decisions: the government aims to conclude them by 28 May 2027.
- Works must be complete by 31 March 2028.
Who can apply
- UK public and private fleets, local authorities and non-profits, including rental and leasing companies.
- You must own or lease at least one UK depot and have operated in the UK for at least a year.
- Your fleet must include, or will include, at least one battery-electric van, HGV or coach.
- A senior leader must approve the application, and you must agree to monitoring and site audits.
- Within a corporate group, each company can apply for up to £1 million per window, but the group total is capped at £3 million in a scheme year.
HGV depots qualify, and so do waste collection depots run for local authorities. Vehicle dealerships do not, except for genuine fleet operations such as parts distribution.
What it does not cover
- Grid capacity and connection costs are not eligible. You must show the site has, or will have, enough capacity.
- Solar generation is not eligible. Battery storage can be, if it is physically and operationally integrated with the chargers.
- Chargers cannot be bought, and civils cannot start, until the grant funding agreement is signed. Existing installations are not eligible.
- Hydrogen refuelling, buses, hybrid vehicles and dealership stock or demonstration charging are out of scope.
- Commercial vehicles must be the primary users. Occasional staff car charging is allowed as a secondary use.
What you will need
- Your operator licence (or, for van-only fleets, BVRLA, FORS or Logistics UK van accreditation).
- Evidence of current or ordered battery-electric vehicles.
- Proof you own or lease each depot.
- Evidence of grid capacity, such as a connection agreement, a network operator letter, or an accepted connection offer.
- A full budget, your contractors, and evidence of financing.
There is no approved installer list for this scheme. You choose your own contractors, but must show value for money and due diligence, such as their accreditations.
Sources: GOV.UK Find a Grant, checked 16 November 2026, and the Depot Charging Scheme FAQ.
What happened to window 1?
The first window, announced in March 2026, paid up to 70% (GOV.UK, 25 March 2026). Trade press reports it closed on 30 June 2026. Window 2 pays 60%, and the government expects rates to keep falling in future windows.
Future windows
Further windows are expected for 2028/29 and 2029/30, with timings and rates to be confirmed in 2027. Treat these as unconfirmed until they are published.
Zero Emission Truck Grant
The truck grant is applied by the dealer as a discount at the point of sale (GOV.UK, checked 16 November 2026). In Great Britain the maximum grant is:
- 4.25 to 12 tonnes: the lower of £15,000 or 20% of the price.
- 12 to 18 tonnes: the lower of £37,000 or 40%.
- 18 to 26 tonnes: the lower of £52,000 or 40%.
- Over 26 tonnes: the lower of £81,000 or 40%.
Large enterprises in Northern Ireland are capped at 30% for trucks over 12 tonnes. Vehicles must have zero tailpipe emissions and at least 96km (60 miles) of zero-emission range.
The Subsidy Advice Unit’s report on the scheme says it runs from 1 April 2026 to 31 March 2030, or until its £877 million budget (shared with the van grant) is used, and proposes a limit of 100 trucks per customer per year (Subsidy Advice Unit report). Rates may change at OZEV’s discretion.
Tax relief
100% first-year allowance on chargepoints
Companies can deduct the full cost of new electric vehicle chargepoint equipment bought before April 2027 (GOV.UK, checked 16 November 2026). Depot Charging Scheme projects can run to March 2028, so check timing with your accountant.
Full expensing on trucks
The 100% first-year allowance for zero-emission goods vehicles ended in April 2025. Companies can claim full expensing on new and unused plant and machinery that is not a car (GOV.UK), which may include trucks. Confirm with your accountant.
Scotland
Scottish Zero Emission Truck Fund (proposed)
Transport Scotland has proposed a fund of up to £240 million over five years, with a first round of up to £110 million between 2027/28 and 2029/30. It would fund consortia only, with at least one private finance provider and four HGV operators, all based in Scotland (Subsidy Advice Unit report, 29 September 2026).
Unlike the Depot Charging Scheme, the proposal covers up to 50% of eligible charging costs including grid connections, battery storage and small-scale renewable generation. Launch dates and final rules are not yet confirmed.
SME Fleet Analysis Support
Transport Scotland’s SME Fleet Analysis Support offers up to £15,000 per fleet for analysis to plan the move to zero-emission HGVs (Transport Scotland, 21 July 2026). Applications are open until 15 January 2027 (Transport Scotland, checked 16 November 2026).
ZEHID: evidence, not funding
The Zero Emission HGV and Infrastructure Demonstrator (ZEHID), run by the Department for Transport and Innovate UK, funded demonstration projects chosen in 2022 (Innovate UK Business Connect). It is not open for new applications, but its findings on costs, charging and grid are worth reading (ZEHID annual report 2026).
What is not available
- We found no dedicated UK fund for public or en-route HGV charging. The Depot Charging Scheme excludes public on-route sites.
- There is no national grant for grid connection costs for depots.
- There is currently no purchase grant for zero-emission coaches.
Making the most of the funding
- Check eligibility now and complete the scheme’s pre-assessment questionnaire.
- Get grid capacity evidence from your network operator as early as possible.
- Design for 60% of chargepoint and civil costs, and budget the rest, including the connection.
- Do not order chargers or start civils before the grant agreement is signed.
- Add solar and battery storage to cut running costs and peak demand. Batteries can be grant-funded; solar cannot. Our solar and EV charging calculator models the savings.
See our electric HGV charging page, our general EV charger grants guide and HGV depot grid connections.
Frequently asked questions
Is there a grant for HGV charging in the UK?
Yes. The Depot Charging Scheme pays 60% of eligible chargepoint and civil costs at fleet depots, up to £1 million per organisation. Window 2 is open from 11 November 2026 to midday on 26 February 2027 (GOV.UK Find a Grant, checked 16 November 2026).
How much is the electric truck grant?
In Great Britain it is up to 40% of the price, capped at £37,000 for 12 to 18 tonnes, £52,000 for 18 to 26 tonnes and £81,000 over 26 tonnes. Trucks of 4.25 to 12 tonnes get up to 20%, capped at £15,000.
Can I start work before my Depot Charging Scheme grant is approved?
No. Chargers can only be bought and civils started once the grant funding agreement is signed. Installations already completed are not eligible.
Does the Depot Charging Scheme fund grid upgrades or solar?
No. Grid capacity and connection costs are not eligible, and solar is no longer supported. Battery storage integrated with the chargers can be eligible.
When does the Depot Charging Scheme close?
Window 2 closes at midday on 26 February 2027, or earlier if the £38 million budget is used up. Works must be finished by 31 March 2028.
Is there HGV funding in Scotland?
Scottish fleets can apply to the UK Depot Charging Scheme. Transport Scotland has also proposed a Scottish Zero Emission Truck Fund for consortia, but its launch date is not yet confirmed.
Get your depot grant-ready
We can help you plan chargers, battery storage and solar around the scheme’s rules and your grid capacity, working with accredited installation partners where required.