For most electric truck depots, the grid connection is the biggest cost and the longest lead time. Chargers can be ordered in weeks, but extra capacity can take months or more.

The government’s ZEHID demonstrator found charging infrastructure to be a key bottleneck, with site issues that were costly, time-consuming and dependent on landowners and network operators (ZEHID annual report 2026).

This guide explains how the process works and how to reduce the capacity you need.

Who you deal with

Distribution network operators (DNOs) run the local electricity network in each region. You need to engage your DNO to arrange a new connection or change an existing one, and the Energy Saving Trust advises doing so as early as possible (Energy Saving Trust).

Some connection work can be done by an accredited independent connection provider (ICP). Your connection offer will show which parts are contestable.

How big a connection?

DNOs group connections by size. For example, SSEN generally treats up to 70kVA as small, 70 to 200kVA as medium and over 200kVA as large (Energy Saving Trust). Larger connections can bring transformer, reinforcement and other requirements that add time.

Cenex gives indicative figures for EV charging connections (Cenex, accessed November 2026):

HGV depots with several high-power chargers will often sit in the large band. Every site is different, so treat these only as a guide.

Who pays for reinforcement?

Since Ofgem’s Access and Forward-Looking Charges reforms took effect in April 2023, customers generally no longer pay for upstream network reinforcement unless the connection triggers a high-cost project threshold (Energy Saving Trust). Connection costs are generally limited to downstream work.

Larger connections also carry ongoing capacity charges, whether or not you use the capacity. Sizing it carefully saves money every year.

Grid capacity and the Depot Charging Scheme

The Depot Charging Scheme does not pay grid capacity or connection costs. Applicants must evidence capacity with one of: a copy of the connection agreement; a DNO letter or email confirming capacity; or a DNO quote and connection offer, with evidence of acceptance, within 2027/28 (Depot Charging Scheme FAQ, checked 16 November 2026).

If you are constrained and cannot upgrade in time, the scheme suggests considering battery-integrated chargers. Integrated battery storage can be eligible for the grant.

Window 2 closes at midday on 26 February 2027 (GOV.UK Find a Grant, checked 16 November 2026), so start the DNO conversation now.

Step by step

  1. Build a fleet plan: vehicles, timing, daily energy and dwell times.
  2. Check your existing supply and half-hourly demand.
  3. Model the charging load with load management, and test phasing options.
  4. Ask the DNO about available capacity and indicative costs.
  5. Apply for a connection offer sized to your phased plan.
  6. Review contestable and non-contestable work and programme.
  7. Line up grant evidence and finance.
  8. Design, install and energise in phases.

Reduce the capacity you need

The Energy Saving Trust notes that well-designed storage may avoid costly supply upgrades and ongoing capacity charges, but storage is finite: once it is used, charging falls back on the grid connection (Energy Saving Trust).

Leased depots

If you lease the site, agree early with your landlord who owns the chargers and connection, and who pays. The Depot Charging Scheme expects the applicant to own the chargepoints and asks for the site owner’s written permission where needed.

Frequently asked questions

How long does a depot grid connection take?

Cenex gives indicative timescales of 8 to 12 weeks for small and medium connections and six months or more for connections above 1,000kVA. Actual timescales depend on your DNO and local network.

How much does an HGV depot grid connection cost?

Cenex gives indicative costs of £60,000 to £2 million for connections above 1,000kVA. Smaller connections cost much less. Every site needs its own quote from the DNO.

Does the Depot Charging Scheme pay for my grid connection?

No. Grid capacity and connection costs are not eligible, and applicants must show evidence of capacity.

Can batteries avoid a grid upgrade?

Sometimes. Battery storage can supply short, high-power peaks and reduce the connection needed, but once it is empty charging depends on the grid supply.

Who should I contact first?

Your distribution network operator. Engaging early helps you understand capacity, cost and timescales before you commit to chargers.

Get help planning your depot power

Tell us about your site, your vehicles and when they park. We will look at your supply, your roof and your options, then send a clear, no-obligation proposal.

See electric HGV charging and HGV and electric truck charging grants.