How long an electric HGV takes to charge depends on three things: how much energy the battery needs, how much power the charger gives, and how much power the truck can accept.
Here is how to estimate it, with an official example, and how to plan a depot around it.
The quick answer
The Energy Saving Trust gives the example of a Volvo FE charging fully in about 1.5 hours on a 150kW DC charger, or 6 to 8 hours on a 22kW AC charger (Energy Saving Trust). Larger trucks with bigger batteries take longer at the same power.
The simple formula
Charging time in hours is roughly the energy needed in kWh divided by the charging power in kW.
For illustration only: a truck that needs 300kWh would take about 2 hours at 150kW, or about 50 minutes at 350kW, before allowing for losses and slow-down near full. Check your own vehicle’s battery size and maximum charging rate with the manufacturer.
Why real charging takes longer
- The truck sets the limit. A truck can only take its maximum charging rate, however powerful the charger.
- Charging slows as the battery fills. Most fast charging happens at lower states of charge.
- Shared power. With load management, chargers at a busy depot may share the available supply.
- Temperature. Very cold or hot batteries can charge more slowly.
AC vs DC for trucks
DC charging is common for heavy vehicles, but AC can still work where trucks park for long periods. The Energy Saving Trust notes that two 43kW AC chargers used together can give a combined 86kW (Energy Saving Trust).
For very fast charging, the Megawatt Charging System is a newer standard for heavy vehicles, with a CharIN maximum of 3.75MW.
Charging options at a glance
- 22kW AC: overnight depot charging where trucks park for many hours. The Energy Saving Trust example is 6 to 8 hours for a Volvo FE (Energy Saving Trust).
- Two 43kW AC chargers together: a combined 86kW, a middle option for some depots.
- 150kW DC: faster turnaround; about 1.5 hours for the same Volvo FE example.
- Megawatt charging: very high power for short breaks and long routes, up to the CharIN maximum of 3.75MW (CharIN).
Questions to ask your truck supplier
- What is the usable battery capacity?
- What is the maximum AC and DC charging rate, and at what state of charge does it start to slow?
- Which connector does it use: CCS, MCS or both?
- How does cold weather affect charging and range?
- What energy use per mile should we plan for on our routes?
Plan charging around dwell time
The best depot plans start with when trucks are parked, not with the fastest charger.
- List each vehicle’s daily energy use from routes and mileage.
- Note when it returns and leaves, and any long breaks on site.
- Choose the lowest charger power that refills it in that window.
- Add high-power charging only where turnarounds are short.
- Check the total against your site’s grid capacity.
Breaks matter too. Drivers must take breaks totalling at least 45 minutes after no more than 4 hours 30 minutes of driving (GOV.UK), which is when high-power top-ups make most sense.
Why slower charging often wins at the depot
- Lower power per bay means a smaller grid connection.
- Charging spread overnight can use cheaper electricity.
- Load management can share capacity across more trucks.
- Battery storage and solar can cover daytime top-ups.
Grants for depot chargers
The Depot Charging Scheme pays 60% of eligible chargepoint and civil costs, up to £1 million, with applications closing at midday on 26 February 2027 (GOV.UK Find a Grant, checked 16 November 2026). See HGV and electric truck charging grants.
Frequently asked questions
How long does it take to charge an electric HGV?
It depends on battery size, charger power and the truck’s maximum charging rate. The Energy Saving Trust example is a Volvo FE charging fully in about 1.5 hours at 150kW DC, or 6 to 8 hours at 22kW AC.
How do I estimate charging time?
Divide the energy needed in kWh by the charging power in kW, then allow extra time for losses and slower charging near full.
Can electric HGVs charge on AC?
Yes, where trucks park long enough. AC charging is slower but can suit overnight depot charging.
Does a more powerful charger always charge faster?
Only up to the truck’s maximum charging rate. Above that, extra charger power makes no difference.
How fast is megawatt charging?
The Megawatt Charging System has a CharIN maximum of 1,250 volts and 3,000 amps, or 3.75MW. Actual speeds depend on the truck and charger.